  Plan Actual Variance Extended
Hardware and Software $78,000 $55,000 -29% $55,500
Development Time 960 hours 985 hours +3% $25,137
Converting Old Files 2000 hours 3240 hours +62% $45,584
Total Direct Costs $126,221
Mgmt/Tech/User Time N/A 1697 hours N/A $40,250
Total Institutional Costs $166,471